Ministry of Railways has sanctioned the Final Location Survey (FLS) for the following projects of South Eastern Railway  for preparation of Detailed Project Report (DPR) at a total cost of 1.4680 Crore.

 

SL Name of Projects Approx. length

(in Km)

Cost in Rs.
1 Doubling of Mohuda Khanoodih Gomoh section 22.4

 

 

44,80,000/-
2 Direct connectivity between Tata Marshalling Yard and Tata-Badampahar route 05.0

 

 

10,00,000/-
3 Double line Bypass from Jakpur to Benapur avoiding Kharagapur and Nimpura Yard with Fly over at Benapur and Jakpur in Down direction to avoid surface crossing 11.0

 

 

22,00,000/-
4 Fly over at Rupsa for connecting Kharagpur – Bangriposi and Bangriposi to Bhadrak to avoid surface crossing. 35.0

 

 

70,00,000/-
  Total 73.4 1,46,80,000/-